Click on the area label (here “Main facilities”) :
The following window pops up:
Click on Add then fill in the fileds 'Name' and 'Style par défaut' of the Task details tab:
In the Dates tab set the Calendar, Start and End dates like below, then click on OK :
Your task is now associated with the area:
To create a summary task, click on the subproject in the left panel explorer of the Gantt chart, then click on the “Add a task” button:
In this example we'll create the following summary task:
After clicking on OK, you can see in the Gantt chart that the task has been created, but as a simple task.
To turn it into a summary task, simply drag and drop a child task into it. Here we'll do it with the “Construction facilities” task:
With Phase Manager, it is possible to create your tasks directly or to import them from an XLS file through the clip-board.
Open the file to be imported (in this case Demo Project V5.xlsx
), then select and copy into the clipboard all tasks data header included:
Explanations:
1/ The summary tasks are imported first (IDs 2 → 6)
2/ Each task is referred to a summary task, via the “Parent” column.
3/ Each task must have a parent: in the absence of a summary tasky, the subproject (here PM-00001) is then mentioned, which is therefore here the parent of the summary tasks.
Go to the menu File > Import tasks/links .
In the import window that opens, insert the data from the clipboard by clicking on the Paste button:
The preview area shows you that the data has been read from the clipboard. You can then assign each column to a Phase Manager field, either manually or by importing an existing exchange profile.
Here we'll load the profile Import ProfileEN.pmx
(delivered with your installation).
Click on the Load profile button:
Then browse your hard drive for the exchange profile and click on Open .
Then check that the display is as follow:
You see that the fields from you data set have been correctly assigned to the corresponding Phase Manager fields; you can click on the Import button at the bottom right of the window and then confirm the import :
Note on the warning window:
A window tells you that some fields have not been imported:this is informative, and concerns the empty fields “Area” and “Dates” for the summary tasks; Area having no meaning, and Dates are inherited from its child tasks:
After closing the import window, you can see that tasks have been imported, and that the WBS matching our imported phases has been created:
Phase Manager 3 enables extensive management of the RoW and impact of tasks. The example below illustrates those new functionalities by creating a daily sequential book.
The task 'RT V1 20+200 - 20+700' below is associated with two areas or axis, namely V1 and V2 :
Here are the details of the settings:
V2 axis :
V1 axis :
On the first two daily pages of the considered 3-day sequence, we can visualize:
Day 1 :
Day 2 :